Salient Features:
PC-I Cost: PKR. 4,362.978 Million
Completion Period: 1.5 Year
Completion Date with DLP: 30th June, 2025
Total Masajid to be Solarized: 5000
Capacity: 10.8 MW
Annual Energy (MWh): 59.4 MWh/Year
Annual Saving: 430 Million/year (Expected)
Current Status:
- Survey of all Sites Completed
- Partial Installations Initiated.
Challenges Faced During Implementation:
- Delays being faced due to restriction on imports under
Pakistan Tariff Codes HS 84 & 85 and processing of LCs.