Salient Features:
Capacity : 157 MW
Design Discharge : 129 m3/s
Gross Head : 154 m
Length of Power Tunnel : 11.8 km
Length of TL : About 2-3 Km Approx
Annual Energy : 767.5 GWh
Annual Revenue : Rs.17,047.54 Million (As per PC-1)
Approved PC-1 Cost : Rs.79,374.85 Million
Contract Cost : Hiring is in Progress
Commencement Date : December, 2020
Anticipated Completion Date : November, 2027