Present Status / Project Progress:
Overall Project Progress : 99%
Land Acquisition : 100%
Detailed Engineering : 100%
Civil Work : 100%
Tunnel : 100%
Power House (E&M Work) : 100%
Switch Yard : 100%
Power Evacuation : 98%
Project is physically completed in all respects since Dec, 2022 but due to connectivity problem and non-approval of EPA, it could not be made operational.