Challenges Faced During Implementation:
After the approval of the project, the districts administration lack in land record and procedure/SOPs for land acquisition in merged areas, therefore, the process of the land acquisition was delayed till the finalization of land acquisition rules 2020 dated July 23, 2020 vide no. REV:V/4/B.J/2019/1726-72. Merged Areas.
Due to COVID–19 pandemic, the process of land acquisition and installation at site were delayed due to the unavailability of NOC’s from districts administration.
In original PC–I, the approved land cost is PKR. 195 million, whereas the actual land cost incurred till date is 119.19 million.
The erection of power transmission line/poles was delayed due to the community observations/ unwillingness.
The variable Law and Order situation, restricted movement and working hours are other factors causing delay in execution work.
Initially sites were not identified. The sites were sought and identified after award of contracts. The identified sites survey was conducted, data was collected and feasibility was evaluated. After due diligence, the district administration of two (2) sub. Divisions i.e. Sub. Division Wazir (Ex – FR Bannu) and Sub Division Bettani (Ex–FR Lakki Marwat) responded that no such market/bazar is available.
The estimates for land acquisition in Sub. Division Darazinda and Sub. Division Dara Adam Khel are still not intimated to office of the concerned Project Director (Solar).
The bill of quantities (BOQ) was also revised on the bases of site requirements and technical grounds and revised PC-I was submitted for further approval.
Challenges Faced During 2022-23:
Land Acquisition and site identification of various Grids e.g. Sararogha bazar,South Waziristan
Law and Order situation and security threats.
Route clearance for Transmission Line from Grid to Market.
Approval of 2nd Revised PC-I.
Works stopped at site due to the Payment Issues to land owner e.g., Kurram, Orakzai and Hassan Khel (FR Peshawar).
Additional; Cost of Transmission Lines and depreciation issues.
Stoppage of work by the locals during construction of Transmission Line.