Approved Financial Evaluation Summary for Project “Rehabilitation and Restoration of 17 MW Ranolia Hydropower Project, District Lower Kohistan -Lot-II
Approved Financial Evaluation Summary for Project “Rehabilitation and Restoration of 17 MW Ranolia Hydropower Project, District Lower Kohistan -Lot-II” are attached below:
Financial Evaluation Summary for Design, Manufacture, Installation, Testing & Commissioning of 132 KV GAS Insulated Switchgear (GIS) and Associated Works at Ranolia HPP District Lower Kohistan PEDO
Approved Financial Evaluation Summary for Design, Manufacture, Installation, Testing & Commissioning of 132 KV GAS Insulated Switchgear (GIS) and Associated Works at Ranolia HPP District Lower Kohistan PEDO are attached below:
Technical Evaluation Summary for Project “Rehabilitation and Restoration of 17 MW Ranolia HPP, Kohistan- Lot-II
Approved Technical Evaluation Report for Rehabilitation & Restoration of 17 MW Ranolia Hydropower Project at District Lower Kohistan Lot-II are attached below.
Approved Technical Bid Evaluation Report ( T-BER) for 6.95 MW Mujahidin Hydropower Project at Barandoo River, District Torghar
Approved Technical Bid Evaluation Report ( T-BER) for 6.95 MW Mujahidin Hydropower Project at Barandoo River, District Torghar are attached below. Download
Minutes of the Pre-bid Meeting on Civil Works Lot#2 for Rehabilitation and Restoration of 17 MW Ranolia Hydro-Power Project – Addendum No. 1
The pre-bid meeting minutes is attached below.
Instructions for Qualified Candidates (3rd Phase)
With reference to the screening test held on September 16 and September 17, 2025, for various BPS-17 and below positions in PEDO conducted by ETEA, all qualified candidates (who have secured 50% or above marks) are hereby informed to carefully read and comply with the following instructions. The last date…
Instructions for Qualified Candidates (2nd Phase)
With reference to the screening test held on September 10, 2025, for various BPS-17 and below positions in PEDO conducted by ETEA, all qualified candidates (who have secured 50% or above marks) are hereby informed to carefully read and comply with the following instructions. The last date for submission of…