Project
Brief
Malakand-III
Hydropower Project was identified after the construction of Auxiliary Tunnel
under Swabi SCARP on the Upper Swat Canal System. The Upper Swat Canal System
was completed in 1918. It emanates from the Swat River at Amandara Head Works
and irrigates 121,400 hectares of land.
Due to
increase in irrigation water demand the Amandara Head Works was upgraded under
the Swabi SCARP and another auxiliary tunnel, parallel to the existing Benton
tunnel was constructed to carry the increased design discharge of 51 Cumecs. In
order to avail this additional discharge for hydropower, before it is fed into
Machai branch, the Malakand-III Hydropower Project having a capacity of 81 MW
was conceived. This project was proposed to be operated in conjunction with the
two existing power stations of Jabban and Dargai keeping in view the variation
in water availability in Swat River.
It is
important to add that subsequent to the feasibility of Malakand-III, it was
identified that 25,000 acres of land can be irrigated under the project, in
addition to hydel benefits. Therefore, from the outlet of sediment excluder of
Malakand-III HPC “Baizai Scheme” was constructed and which irrigates about
25,000 acres of land.
Malakand-III
Hydropower Project was completed in 2008 and interconnected with National Grid
through 132 kV Dargai Grid Station. The power generated is being sold to NTDC
under a Power Purchase Agreement (PPA) with NTDC for 25 years. The rate for
sale of power to NTDC has been determined by NEPRA. The Project had achieved
its Commercial Operation Date (COD) on November 1, 2008.
Overall, the Malakand-III
Hydropower Project stands as an important source of renewable energy,
contributing to the power supply of the region while also facilitating
irrigation for thousands of acres of land. It exemplifies the successful
utilization of water resources for both electricity generation and agricultural
development, making it a crucial infrastructure project for the region's
socio-economic growth. Till date the power plant has generated over 40 billion
revenues to the government exchequer.
|
Capacity |
81 MW |
Design Discharge |
51 m3/s |
Net Head |
181 m |
Length of Power Tunnel |
3.3 km |
Annual Energy |
549 GWh |
Project Cost |
Rs. 5750 Million |
COD |
1st November
2008 |
Tariff |
|
Levelized
(1-25 Years) |
4.0294 Rs/kWh |
Innovation & Achievements
Innovation Steps (Indigenous Major Overhauling)
For the first time,
the major overhauling of unit # 3 was carried out without foreign technical
assistance. Expertise from the local market were engaged through O&M
Contractor and successfully completed the major overhaul. This innovative step
improve the turbine efficiency of the hydropower plant by up to 15%. As a part
of the efficiency improvement efforts, stability in machine operation was
achieved. This is crucial for smooth and reliable power generation without
unexpected shutdowns or disruptions.
Challenges Faced During Year (2022-23)
Due
to heavy rain and flooding in upper swat canal during the month of August 2022
arrival of heavy trashes, sand/ silt in forebay and sediment, resulting in
choking of trash racks and cooling water systems. Due to influx of heavy sand
the underwater parts of turbines such as head cover, wicket gates, bottom ring,
and runner are eroded by abrasive sand particles. This led to multiple plant
shutdowns during the peak season and a substantial loss of turbine efficiency.
The unit operated at partial load due to unstable bearing temperatures and
heavy vibrations in the unit.
Achievements
1. The initiatives for turbine
efficiency improvement and stability in machine operation resulted in an
improvement in the plant availability factor. This indicates that the
hydropower plant was operational and available to generate electricity more
consistently. The implementation of innovative steps, particularly the
improvement in turbine efficiency, led to an increase in the annual energy
generation of the hydropower unit. As a result, it can be expected that more
electricity will be generated in the next financial year (Financial Year
2023-24).
The major overhauling of unit # 3 was
completed in a short period of 50 days. After successful completion of the
major overhauling, Unit #3 was synchronized with the National Grid and operated
at its maximum load of 27.10 MW. This achievement highlighted the restored
capacity of the unit to generate electricity at its full capacity.
2. The successful completion of the
Demonstrated Complex Energy Test (DCET) conducted from June 08 to June 09, 2023
witnessed by CPPAG test witnessing Team. The test demonstrated that the
hydropower complex can generate energy equivalent to 81.480 MW.
Overall, the innovative steps and achievements at the Malakand-III
Hydropower Complex signify the commitment to
improve plant efficiency, optimize operations, and to achieve the generation
capacity.