Project Brief
Lawi Hydropower Project is a run-off river project which was
identified by WAPDA and the feasibility study was completed in 2007-2008. The
PC-I cost of the project is Rs. 20,087.50 Million. The EPC Contract of the
Project has been awarded to JV of M/s Sichuan (Chinese Firm) – Sarwar
(Pakistani Firm) – Silian (Chinese Firm) – Chongqing Luyang (Chinese Firm) and
its commencement date is November 3, 2016.
The Project site is located in Drosh
Tehsil on Shishi River (a left tributary of Chitral River) which is about 40 Km
short of Chitral city. The Powerhouse of the project is located on N-45 road in
Basnak village at a distance of 4 Km from Drosh Town whereas the Weir is
situated in Lao Nisar Village at 18 Km from Powerhouse.
Salient Features
Location |
Village Lawi, Drosh, District Lower Chitral |
Generating Capacity |
69 MW |
Design Discharge |
20 m3/s |
Net Head |
398.5 m |
Tunnel Length |
12,117 m |
Annual Energy |
308 Gwh |
Approved Tariff |
Rs. 7.94/kwh |
Revenue Per Year |
Rs. 2,400 Million (expected) |
Progress (Physical) |
52.30% |
Project Status
·
The
construction activities have been resumed in January, 2023.
·
Currently
the Project progress is 52.30% as on June 30, 2023.
·
Project revised
completion is December 31, 2024.
Challenges Faced During Construction
·
Delay in
issuance of explosive NOC by Local Administration
·
Closure of
Sust border affected the import of construction machinery from China
·
Occurrence
of flash flood in shishi river (weir site)
·
Stoppage
of work at Adit tunnel-3 by Locals
·
Suspension
of work due to outbreaks of covid-19 in Pakistan causing force majeure
situation
·
Security
reasons including Dasu incident with Chinese
·
Poor
geological conditions encountered in tunnel during excavation
·
Due to
modification of tunnel alignment, additional construction of Adits with
required access roads & site camps took considerable time.
· Design modification of powerhouse foundation
· Stoppage of work by the Contractor due to devaluation of Pakistani rupee and abnormal price hikes of construction material.
· The project was delayed
by more than one (1) year due to price hike and dollar rupee parity. Issue of
termination or continuity of contract was referred to policy board chaired by
CM KP, wherein approval for financial help and escalation was granted, after
which the work has been resumed at site.