Project Brief
Pehur Hydropower Complex is
constructed at the out let of Gandaf Tunnel emanating from Tarbela Reservoir to
feed the Pehur High level canal PHLC located in District Swabi, 1km south of
Gadoon Industrial State.
The idea of Pehur Hydropower Project
(PHPP) was conceived in 1993 during the feasibility study of the Pehur High
Level Canal (PHLC) Project. Technical feasibility study for PHPP was completed
in May 2001 and the PC-1 of the project was approved in February 2005. The
construction work on the project started in November 2005 and was completed in
July 2009. The total cost of the project was around 900Million PKR of which 50%
was financed by Sarhad Hydel Development Fund (HDF) and 50% by Annual
Development Program (ADP).
The Generation License [No.GL
(Hydel)/08/2009] was granted by National Electric Power Regulatory Authority
(NEPRA) to Sarhad Hydel Development Organization (SHYDO) for 18 MW Pehur
Hydropower Plant in November 2009.
The project
achieved the COD on 1st
March, 2010. Pehur HPC interconnected with 132KV Gadoon grid station.
The annual generation of the plant is 57.7 GWh. So far Pehur HPC has generated
642.052 GWh of energy.
|
Salient Features
|
Capacity |
18 MW |
Design
Discharge |
10.09 m3/s
(two high head units) 15.75 m3/s
(one low head unit) |
Net Head
(high head units) |
68m |
Net Head
(low head unit) |
44m |
Length of Penstock |
4.7 km |
Annual
Energy |
57.7 GWh |
Project
Cost |
Rs.900
Million |
COD |
1th
March 2010 |
NEPRA Approved Tariff |
|
Levelized
(1-25 Years) |
Rs.
3.7670/kWh |
EPA with
Bulk Power Consumer; (From June 2020 up to now) |
|
Wheeling Tariff |
|
Tariff |
Rs. 7.5514/kWh |
Challenges Faced
During Year (2022-23)
Pehur
HPC never achieves its annual generation target i.e. 57.7 GWhr, due to the following two reasons.
1) Annual
canal closure period (January & February).
2) No
irrigation demand at the Pehur high level canal during monsoon season.
3) Frequent shut down of power house due to
accidental fall of locals in the canal particularly during summer season.
Innovation & Achievements
1)
The
Historic achievement in Generation for the year 2022-23 is 51.26 GWh, as a
result of optimum use of Pehur canal flows.
2)
Wheeling phase-I of power generated by 18 MW Pehur HPC to local
industries helped industrialization in the Khyber Pakhtunkhwa province that
provided industrial sector an opportunity to become competitive in the global
market.