Project
Brief
The Reshun Hydropower Project is located in District Chitral at
distance of 52 km north of Chitral. The equipment of 2.8 MW was provided by GTZ
(Pak German Technical Cooperation) as grant. The powerhouse was commissioned in
1999 as part of social uplift project in Chitral region for supplying of
electricity to predominately upper Chitral region and some parts of lower
Chitral through its own transmission and distribution system with a tariff rate
of Rs 1.40/kWh. With increase in load demand of the area, the project capacity
was subsequently enhanced to 4.2 MW in 2006. Till July 2015, the project was
responsible to supply electricity to over 18,000 consumers at the cheapest
tariff through its own transmission and distribution system of 33 kV
transmission line as per following details:
T/L Feeders |
Details |
Feeder-I |
Reshun-Chitral
(Joti Lasht) Length of
the TL = 66km, Villages = 18 Nos. |
Feeder-II |
Reshun-Turkoh/Morkoh-Madak Length of
the TL = 71km, Villages = 29 Nos. |
Feeder-III |
Reshun-Chitral
(Joti Lasht) Length of
the TL = 66km, Villages = 18 Nos. |
|
The devastating Flood occurred on July 16 and July 25, 2015 in
Chitral valley, which severely damaged the power plant including intake
structures and Electro-Mechanical equipment. The power plant has been
successfully rehabilitated in year 2021 using the same foundations and
efficient E&M machinery and therefore the generation capacity of the power
plant is enhanced to 4.8 MW. Currently, the power plant is providing
electricity to over eighteen thousand (18,000) consumers of District Upper
Chitral. As the project was a social uplift project of GoKP for Chitral,
therefore the power tariff rate was the lowest, starting from Rs 1/kWh to
4.69/kWh till 2022-23. The project was operated on no profit no loss basis
since year 1999. Currently, due to the enormous increase in the load demand of
the area, the bridge between generation and demand has been met from the
Jutilasht grid of PESCO. MOU has been signed under the leadership of Federal
Minister for Energy & Power and Governor Khyber Pakhtunkhwa to implement
the tariff rates of PESCO in line with the lower Chitral, till the decision of
the NEPRA for continuing special waiver in the tariff rate for Upper Chitral
(PEDO) consumers. The increase in the tariff has been implemented since June,
2023.
Salient Features
Cost of the
Project |
Rs. 394
Million |
Completion
Year |
1999 |
Cost of
Rehabilitation |
Rs. 1054
Million |
Maximum
Capacity |
4.8 MW |
Annual
Energy |
25 GWh |
Tariff |
4.69/kWh |
* The project is being run on no profit no loss basis
to provide the cheap electricity to the locals of upper Chitral.
Challenges