Pakhtunkhwa Energy Development Organization


Investment opportunities under CPEC

      Construction of 7 Hydropower projects in Khyber Pakhtunkhwa

Projects with Feasibility Study Completed

S. No.

Name of Scheme

Capacity (MW)

Est. Cost in Million

1

Muigram-Shaghore HPP Chitral

64

182

2

Istaro-Booni HPP, Chitral

72

276

3

Toren More Kari HPP Chitral

350

753

4

Jameshill Toren More HPP Chitral

260

616

5

Gahrit-Swir Lasht HPP Chitral

377

1811

 

Total

1,123

3,638

 

 

                      Project without Feasibility Study

S. No.

Name of Scheme

Capacity (MW)

Est. Cost in Million

1

Torcamp-Guddubar HPP Chitral

409

1534

2

Kari-Mushkur HPP, Chitral

446

1748

 

Total

855

3282

 

 

   Feasibility & Construction of 500 KV Grid stations at Drosh and Chakdara & 500 Transmissions line of 225km between Grids Cost of Drosh

Grid Station:                            US$ 40.0 M

Cost of Transmission Line:       US$ 112.5 M

Cost of Chakdara Grid Station: US$ 40.0 M

Total Cost:                              US$ 192.5 Million

 





Contact Us


Postal Address
Plot# 38, Sect B-2, Phase-5 Hayatabad Peshawar.
Phone: +92-91-9217330 Fax: +92-91-9217329
Email
info@pedo.pk